Getting closer... 04/19/2012
We are in the home stretch now... the platform has been stained and coated with polyurethane; today the electricians turned on the power and began troubleshooting the lights. We also fine-tuned the projectors today. Latest Pictures... 04/16/2012
Touch-up repairs 04/06/2012
No new pictures right now... a lot of touch-up repairs are being done before the painting is finished. There won't be many major visible changes going on until everything is finished in the walls and ceiling, and they are ready to work on the floors. Primer, Finally! 04/03/2012
Almost Ready to Paint... 04/03/2012
On Monday, the trimwork on the walls was completed, the platform stairs were closed in, and the platform walls were capped and trimmed. The paint crew put primer on all the exposed wood, and painting is expected to begin on Tuesday. Lights and Trim Pictures... 03/30/2012
Progress... 03/28/2012
Today the electricians worked on the preparation work that has to be done before the lights are hung. Also, the finish carpenters began doing the trim work. Ready for Paint and Lights... 03/22/2012
The walls have been finished, and so we anticipate that painters, finish carpenters, and electricians will begin work very soon on the final stages of our renovation. Stay tuned! Getting the Walls Ready... 03/13/2012
Friday's Work... 03/09/2012
The electricians were at it again today, and the drywall finishing crew started the process of taping and bedding the walls. Also, the carpenters began putting the curved face on the platform steps. | AuthorLumpkin Road Baptist Church Archives |